How to manage the visibility of 2D drawings (including hide/show) in your site plan?

To control the visibility or hide/show 2D drawings in your site plan, you can use the following methods:

Method 1: Control Visibility using the 2D Drawing Overlay Shortcut Option:

  • Double-click on the desired drawing in your site plan. Alternatively, you can follow these steps:
    • Click on "Project Setup" in the command dock.
    • Select "Drawing Overlay."
    • Click on the three dots on the drawing you want to control.
    • Choose "Edit."

1.png

  • In the right-side menu:
    • Check the box labeled "Disconnect from timeline." This will disable the drawing's connection to the timeline, allowing you to manage its visibility independently.
    • Quick Tip: You can adjust the opacity of your drawing by using the 'Opacity' slider or by entering any value between 0 and 100 in the opacity field.

2.png

  • To temporarily show or hide drawings:
    • Access the Tools menu from the top-left corner of the site plan interface.
    • Select "2D Drawing Overlay."
    • A list of drawings disconnected from the timeline will appear. The show/hide status of each drawing is indicated by a checkmark symbol.
    • To show a drawing, simply click on its name in the list. The drawing will appear in the viewer with a checkmark symbol in front of it.
    • To hide a drawing, click on its name again in the list. The drawing will disappear from the viewer, and the checkmark symbol will be removed from the front.

Method 2: Control Visibility by Sequencing Drawings between Milestones:

  • Double-click on the desired drawing in your site plan. Alternatively, follow these steps: 
    • Click on "Project Setup" in the command dock.
    • Select "Drawing Overlay."
    • Click on the three dots on the drawing you want to control.
    • Choose "Edit."

3.png

  • In the right-side menu:
    • Under the Timeline section, use the "From" and "To" labels to define the first and last milestones during which you want the drawing to be visible.
    • Note that the drawing will be visible between all the defined milestones.
    • Quick Tip: You can adjust the opacity of your drawing by using the 'Opacity' slider or by entering any value between 0 and 100 in the opacity field.

4.png

  • To temporarily hide or show a 2D drawing sequenced between milestones:
    • Right-click on the drawing and select "Temporary Hide," or select the drawing and press the "H" shortcut key.
    • Alternatively, open the model browser, go to the Site Planning tab, expand the Drawing Overlay node, right-click on the desired drawing, and choose "Temporary Hide," or press "H."
    • To reset the temporary hide/show status of the drawing:
      • Open the model browser and click on the reset temporary hide button located in front of the hidden drawing's name.
      • The drawing will then reappear in the viewer.

5.png

Was this article helpful?