Earthwork in cmBuilder modifies terrain using Earthwork Operations such as Cuts, Fills, Ramps, and Trenches. It helps you simulate excavation stages across Milestones, visualize how the site evolves over time, and generate volume takeoffs for planning and analysis.
In this article, we cover:
- Earthwork Overview
- Create a Cut or Fill
- Create a Ramp
- Create a Trench
- Sequencing Earthwork Operations
- Order of Operations (Boolean Logic)
- Earthwork Takeoff
- How to Customize the Color of Earthwork Operations
- Video Tutorials
- Tips & FAQ
Earthwork Overview
Earthwork in cmBuilder allows for modification of terrain and review of earth quantities. Click Terrain (1), Earthwork (2) to access the Earthwork Sidesheet. From the Sidesheet, the following can be accessed:
- Earthwork Takeoff (3): View volume report and export data.
- Earthwork Settings (4): Configure excavation settings such as boundaries, colors, and surfaces.
- Earthwork Operations (5): There are six operation types: Cut, Fill, Cut & Fill, Trench, Positive Ramp, and Negative Ramp.
Create a Cut, Fill or Cut & Fill
A Cut removes material from the terrain, a Fill adds material to the terrain while a Cut & Fill does both; the boundaries of all three operation types are defined in a sketch. Use Cut & Fill to level the terrain in a single operation instead of creating separate Cut and Fill operations. Launch the Earthwork tool to access the Earthwork Operations:
- Under Add Operations, select Cut (1), Fill (2) or Cut & Fill (3).
- Click in the terrain (4) to start the operation and set the sketch elevation: the Cut top/Fill bottom.
- Sketch the boundaries of the operation using the sketch tools (5) (Line, Smart Arc, Circle etc.)
- The sketch should contain one or more closed polygons. Sketch Lines/Arcs must not intersect.
- Click Confirm (6) to finalize the sketch, then continue to adjust the other Cut/Fill settings.
Cut Settings
Cut settings define the excavation depth, elevation, and placement of a Cut operation. These options determine how much material is removed from the terrain and how the resulting excavation surface is positioned relative to the original topography.
-
Choose either Cut to Depth (6) or Cut to Surface (7).
- Cut to Depth creates a Cut with a flat bottom.
- Cut to Surface creates a Cut where the bottom surface is parallel to the original topography, but offset.
The Sketch Elevation (8) defines the Cut top. This can be adjusted using the input field or the Select from 3D (crosshair) (9).
-
Set the Cut depth:
For Cut to Depth, provide the Cut Depth (10), or alternatively provide a Bottom Elevation (11). You can also use the Select elevation from 3D viewer (12) to pick values directly.
For Cut to Surface, provide an offset and choose the reference surface to use for the offset. You can select cmBuilder Default or a custom Terrain Reference Surface. To learn how to create a Terrain Reference Surface, see 2.7 Terrain Reference Surface.
From the Timeline section (13), set the Milestone when the operation will appear. The Step option (14) sets the sequence when there are multiple Earthwork Operations within the same Milestone.
Fill Settings
Fill settings define how material is added to the terrain to raise its surface. These options control the fill height, elevation, and reference surface, determining how the resulting fill area aligns with the surrounding topography.
-
Choose either Fill to Height (1) or Fill to surface (2).
- Fill to Height creates a Fill with a flat top.
- Fill to surface creates a Fill where the top surface is parallel to the original topography, but offset.
The Sketch Elevation (3) defines the bottom of the Fill. This can be adjusted using the input field or the Select from 3D (crosshair) (4).
-
Set the Fill height:
For Fill to Height, provide the Fill Height (5) or alternatively provide an Elevation (6). You can also use the Select elevation from 3D viewer (7) to pick values directly.
For Fill to surface, provide an offset and choose the reference surface to use for the offset. You can select cmBuilder Default or a custom Terrain Reference Surface. To learn how to create a Terrain Reference Surface, see 2.7 Terrain Reference Surface.
From the Timeline section (8), set the Milestone where the operation will appear. The Step option (9) sets the sequence when there are multiple Earthwork Operations within the same Milestone.
Sloping Adjustments for Cut and Fill
Sloping adjustments control the slope of the walls created by Cut and Fill operations. These settings allow the excavation or fill boundaries to follow specified slope ratios, apply slopes to individual walls, and maintain vertical walls where required.
Click Adjust (1) to set wall slopes for both Cuts and Fills. Select either No Slope (2), Slope In (3), or Slope Out (4). Adjusting the slope is not available for Cut/Fill to surface.
Choose whether to Apply to all walls or define slope ratios for individual walls via the dropdown (5).
Set the Slope ratio (6) for all walls, or adjust values per wall if needed.
Use the Walls to slope section (7) to include or exclude specific walls. Uncheck any walls that should remain vertical — this can also be done by clicking the bubbles in the 3D Space (A, B, C, D, E, F) (8).
Create a Ramp
Ramps are meant to provide vehicle access to the bottom of a Cut or top of a Fill. Ramp operations only become available to insert after first creating a Cut or Fill. Launch the Earthwork tool to access the Earthwork Operations:
- Under Add operations, select Positive Ramp (1) or Negative Ramp (2).
- Position the Ramp against a wall of a Cut or Fill. It will appear blue where allowed and red otherwise.
- Click to place the Ramp. After placing the Ramp, configure the following Ramp settings.
- From the Timeline section, select the Milestone (3) from which the Ramp will be visible in your Scenario. You can also adjust the operation’s order within the selected Milestone using the Step option (4).
- Use the Color/Texture (5) settings to define the visual appearance of the Ramp.
- Include as earthwork volume (6): Turn ON to include Ramp volume in the Earthwork Takeoff.
-
To access further settings click Adjust (7). Adjustments include:
- Define Width (8), Height (9), and Percent grade (slope) (10)
- Define Stable soil angle (side-wall slope ratio) (11), Set X as 0 for a vertical side angle.
Create a Trench
A Trench allows you to create linear excavations by defining a path and selecting a cross section profile. This is typically used for utilities or narrow excavation areas, but can also be used for pad footing in a linear array. To create a trench, first launch the Earthwork tool to access the Earthwork Operations:
From the Earthwork Sidesheet, choose Trench (5).
-
Define the Trench path using the sketch tool. Sketch a polyline that does not intersect itself. The polyline can include angled corners and arcs.
When creating a new Trench the sketcher will launch automatically after adding the Trench.
To edit an existing Trench's path, launch the sketcher from the settings panel using Edit Sketch (1).
💡Note: Trench geometry is defined by a profile swept along a path. The profile and the path can be customized. Watch the video tutorial on creating a trench for a step-by-step walkthrough.
Trench Profile
Select the Trench profile - there are 2 types of Trench profiles straight walls and sloped walls. To change profiles, click on the icon displaying the current Trench profile. From the profile picker, select your desired option. The 3D space will update in real time, allowing you to see the changes instantly.
Straight trench: Straight Trenches have only one setting: Trench Width Bottom.
- The Trench will have a consistent width -the width at the bottom is the same as the width at the top.
Sloped trench: Sloped Trenches have two settings: Trench Width Bottom and Wall Slope Ratio.
- Use the Trench Width Bottom setting to define the width at the bottom of the Trench.
- The Wall Slope Ratio, sets the rise/run of the walls with respect to the Trench depth . e.g. 1:1 results in walls sloped at 45° (from vertical), while 2:1, results in walls sloped at 30° (from vertical). 1:1 ratio is less steep than 2:1 meaning 1:1 results in a Trench that is wider at the top than 2:1.
Sloped Trench Bottom
A sloped Trench is a Trench whose depth increases along its path, starting from the beginning of the path as defined in the sketch. To set the Trench slope, follow these steps:
- From the Sloped Bottom tab (1), set the bottom slope of the Trench by changing the Grade setting (2).
- By default, the grade is flat (set to 0%), a higher percentage creates a steeper slope.
Trench Profile
Sequencing Earthwork Operations
After creation, Earthwork Operations are listed in the Scenario Tree under Map & Earthwork organized per Milestone. From the tree, operations can be dragged and dropped to re-sequence them, and opened for editing.
To re-sequence (re-arrange in time) one or more Earthwork Operations:
- Hover over a selected operation to reveal the drag handle (1).
- Click and hold the handle, then drag the selected operation(s).
- Use the purple line (2) to identify the desired position.
- Release to move the selected operation(s) together.
- To affect temporary visibility, adjust sequencing or edit settings of an existing Earthwork Operations click the 3-dot menu (1) or double click on an Earthwork Operation to manage it. The following actions are available:
- Edit (2): Reopen the operation to view and edit the operation settings.
- Begin from this milestone (3): Assigns the Earthwork Operation to appear at the current Milestone.
- Temp hide (4) : Temporarily hides the Earthwork Operations.
- Temp. hide earthworks after (5): Temporarily hides all the operations following the selected operation.
- Copy (6): Copies the selected Earthwork Operations.
- Paste (7): Pastes the copied Earthwork Operations.
- Create fill from cut (8): Creates an Earthwork Fill Operation to backfill the selected Cut.
- Lock all earthwork operations (9): Locks all Earthwork Operations.
- Delete from site plan (10): Permanently remove the operation from the Scenario.
Order of Operations (Boolean Logic)
The Earthwork Operations (Cut, Fill, Ramp, Trench) are applied one after the other, building on previous operations to modify the shape of the original map terrain. Because operations are applied in sequence, each operation is modifying the map terrain that results from the last operation. This means the order in which operations are arranged in the Tree determines the final shape.
Examples:
When Cut 02 (1) is applied before Fill 01 (2), the terrain is first excavated and then partially filled.
- When the order is reversed (Fill 01 before Cut 02), the final terrain shape and total excavated volume change significantly.
This demonstrates that changing the sequence of operations impacts both the visual outcome and the calculated earthwork volumes.
Earthwork Takeoff
The Earthwork Takeoff provides a summary of the volumes affected by Earthwork Operations across all Milestones. The Overview tab sums volumes within each listed Milestone, while the Detailed Breakdown tab lists volumes of each operation separately. Both allow for export to CSV.
- Click Earthwork Takeoff (1) from the Earthwork Sidesheet.
- The Earthwork Takeoff panel opens to the Overview tab (2).
- Set a Swell Factor (3) – percentage adjustment representing the increase in volume/decrease in density.
- Check Project Total Volume (4), including:
- Compact Volume
- Loose Volume
- Scroll through the Milestone Breakdown table (5) to view volume data summed by Milestones.
- Click Export (6) to download the breakdown as a .csv file.
- Switch to the Detailed Breakdown tab (7) to view a tabular breakdown of each operation, including Milestone and volume data.
- Export is available to download the detailed data as a .csv file.
How to Customize the Color of Earthwork Operations
Earthwork Operation colors can be customized to improve their appearance. The color settings allow separate colors to be assigned to the top/bottom and side surfaces of an operation. To change an operation's colors:
- Start by creating a new Earthwork Operation or editing an existing operation to display its Sidesheet.
- In the Color section (1), there are two color blocks, initially set to the default excavation color
- The first block controls the color of the top/bottom surface(s).
- The second block controls the color of the side/vertical surface(s).
- Click the desired color block (2) to access the color picker and select your preferred color.
- Click the Done (3) button. The selected colors will be applied to your excavation operation.
Video Tutorials
Watch the following videos for step-by-step guidance on creating and managing earthwork operations.
Creating a Trench
Watch this video to learn how to create a Trench.
Creating a Backfill to the Original Map
Watch this video to learn how to create a backfill to the original map.
Tips & FAQ
Creating Excavation Lifts and Benching
Simulating excavation in lifts helps you visualize the construction process and manage material movement more effectively. This approach improves planning, sequencing, and communication across project stages.
Follow these steps to create excavation lifts:
- Create the initial Cut by sketching around the building perimeter or excavation footprint.
💡 Tip: Use the Project from 3D tool within the sketch to quickly project elements like slab edges from your model.
- Set the Cut depth to match the desired lift height (e.g., 10 ft).
- Right-click the Cut in the Scenario Tree or on the scene, then select Copy (1). Next, click Paste (2) and click again in the scene to place the duplicated operation.
- Click and drag the duplicated Cut into the subsequent Milestone and edit the depth to 10ft.
💡Note: If you are creating many lifts, you may wish to apply a slight offset to the sketch to avoid co-planar faces and improve performance. See Optimizing your earthwork.