In this tutorial you will learn about the concept of milestones, and how milestones are used to create the steps of the site plan simulation.
Summary
- The site plan simulation is created by assigning project tasks to time-steps known as milestones
- Use the milestone manager, located in the top center of the screen to create and edit milestones manually or import a schedule to automatically convert scheduled tasks into milestones
- Upon creating the scenario the site has one default milestone - 'Project Start'
Milestone Management
- See edit options from the three dots on the milestone card
- To access the milestone manager table view: Click the three dots, and select Project Schedule
Â
To add a new milestone; either:
-
Click the plus button [+]
- Enter a name and date and press enter (or click off) to confirm
-
From the table view, click the three dots on an existing milestone
- +Add milestone
- Select either Add before or Add after, the existing milestone
- Import Schedule
To edit a milestone; either:
- Double click the name or date on the milestone manager
-
Or, click the three dots, followed by Edit name and date
- Click Delete to remove the milestone
- Press enter (or click off) to confirm
- From the table view, double-click the millstone name or date
-
Or, click the three dots on the milestone
- Click Edit name or Edit date
- Click Delete to remove the milestone
To bulk delete milestones:
- Select the milestones you wish to remove
- Hold Ctrl to select multiple milestones
- Or, hold Shift to select a range
- Right-click on the selected milestones
- Click Delete to remove them all at once
đź’ˇ Note: Timeline items (such as models, zones, labels, resources, etc.) use milestones as start and end dates. If a milestone is deleted, any item linked to it will reset: start dates revert to the beginning, and end dates extend to the end of the timeline. After deleting milestones, you may need to review and adjust the resource visibility.
Excavation operations do not have end dates. If you delete a milestone, the operation moves to the next milestone or if there isn’t one, it moves to the previous milestone. Excavation items are never deleted, they are simply reassigned to another milestone.
View & Navigation Options
To navigate through the milestones:
-
Click the side arrows [<] [>] on either side of the card to move forward or backward
- Alternatively, use the key shortcut of CTRL + L/R arrow keys
- Click Go to milestone to navigate to a selected milestone in the table view
- Click Current milestone to go to the nearest milestone to today's date
To customize the milestone view:
-
To change the milestone index - click the three dots on the milestone manager, followed by View
- Select from weekly (wk), monthly (mo), or a custom index (ms) to show on the milestone manager
- To see all milestones - click the three dots on the milestone manager, followed by Multiple View
- Finally, as mentioned, to see the table view, click the three dots, followed by Milestone manager
What is a Milestone?
- A milestone is the name cmBuilder uses to refer to a phase of work in the logistics or construction plan
- cmBuilder can be analogized to a flip-book animation, where each page is a milestone, and the development of the site will be shown in the final presentation
- A milestone needs to be created to show changes occurring, and thus each scheduled stage of work
Example Sequence:
A simulation attempting to capture the major stages of work may include some of the following milestones:
- Site setup and Mobilization
- Excavation (1, 2 , etc.)
- Foundation
- SOG
- Level 1
- Level 2
- Level 3 and so on
- Envelope
- Podium
- And so on
Further Reading:
Model Browser (Tree) - For more information on using the model tree to sequence the building model
Resource Sequencing - For more information on how to sequence resources
Â
Comments
Please sign in to leave a comment.